NASA released the first AAP schedule. It envisioned 26 Saturn IB and 19 Saturn V
AAP launches. Among these would be three S-IVB/Spent-Stage Experiment
Support Modules (ie., wet Workshops), three Saturn V-boosted orbital
laboratories, and four Apollo telescope mounts. The initial AAP launch was
slated for April 1968, The schedule was predicated upon noninterference with
the basic Apollo lunar landing program, minimum modifications to basic Apollo
hardware, and compatibility with existing Apollo launch vehicles.
Apollo Applications Program Schedule ML-4, NASA Hq, 23 March 1966
---------
At the time the SAA Program Office circulated its memo, the first Apollo lunar landing
attempt was expected in late 1967 or early 1968. NASA, the memo explained, had
ordered from its contractors 21 CSMs, 15 LMs, 12 Saturn IBs, and 15 Satur Vs for
delivery between 1966 and 1970. Most were intended for ground and flight tests.
The SAA Program Office assumed that four Saturn IBs (designated AS-209 through
AS-212), six Saturn Vs (AS-510 through AS-515), and their associated CSM and LM
spacecraft would remain unused afer the first successful piloted Moon landing, and that
these would immediately become available for AAP missions. Basic Apollo CSM and LM
spacecraft would be modified to achieve new goals by the installation of "overlay kits.
Building upon these assumptions, the June 1966 memo described two possible AAP
Program schedules. The Case 1 schedule assumed that no Saturn-Apollo hardware
beyond that ordered for the Moon program would become available before late 1968 and
that only enough AAP missions would be flown to accomplish minimal AAP goals. Case 1
missions would not necessarily serve as a bridge for linking Apollo lunar missions with a
new piloted program in the mid-to-late 1970s. Even with these limitations, the SAA
Program Office envisioned that Case 1 would see 21 Saturn IB and 16 Satu V launches
in the AAP by the end of 1973.
The more ambitious Case II schedule would see "an early extensive utilization of Satur
Apollo capabilities, with an earlier focus on a post-Apollo national space objective (such as
a prototype of a space station or a planetary mission module). Case II would see 26
‘Saturn IB and 17 Saturn V rockets launched from KSC before the end of 1975.
Saturn/Apollo Applications Program Summary Description," memorandum with
attachments, MLD/Deputy Director (Steven S. Levenson for John H. Disher), Saturn
Apollo Applications, NASA Headquarters, to George M. Low, Manned Spacecraft Center,
Leland F. Belew, Marshall Space Flight Center, and Robert C. Hock, John F. Kennedy
‘Space Center, 13 June 1966
---------
NASA Hq issued a schedule which introduced the cluster concept into the AAP
design. The cluster concept consisted of a Workshop launch following a manned
CSM launch. Six months later, a LM/ATM launch would follow a second
manned flight. The LM/ATM would rendezvous and dock to the cluster, the
first Workshop launch was scheduled for June 1968.
The schedule called for 22 Saturn IB and 15 Saturn V launches. Two of the
Saturn IBs would be launched a day apart—one manned, the other unmanned.
Flights utilizing two Saturn V Workshops and four LM-ATM missions were also
scheduled.
NASA Hq Schedule, 5 December 1966
---------
Ata NASA Hq briefing, Associate Administrator for Manned Space Flight George
E. Mueller stated that NASA planned to form an embryonic space station in
1968-69 by clustering four AAP payloads launched at different times.
NASA Apollo Applications Briefing, 26 January 1967
---------
Some significant features of a revised Apollo and AAP-integrated program plan
were: CSM would be available to support the first four AAP launches; AAP-1/
AAP-2 in early 1969 were to accomplish OWS objectives; AAP-3/AAP-4 in
mid-1969 were to accomplish the 56-day ATM objectives in conjunction with
reuse of the OWS. Two additional AAP flights were planned for 1969 to revisit
the OWS and the ATM using refurbished command modules flown initially on
Earth-orbit Apollo flights in 1968. AAP missions planned for low Earth orbit
during 1970 would utilize two dual launches (one manned CSM and one un-
manned experiment module per dual launch) and two single-launch, long-duration
CSM to establish and maintain near-continuous operation of the OWS cluster
and a second ATM. 4 May 1967
---------
Required changes in the Apollo Applications Program flight schedules resulted
in plans for the Earth-orbital test of the lunar mapping and scientific survey
(LM&SS) as part of a single launch mission unrelated to the Orbital Workshop.
‘The mission would have the primary objective of conducting manned experi-
ments in space sciences and advanced technology and engineering, including
the Earth-orbital simulation of LM&SS lunar operations. The LM&SS would
be jettisoned after completing its Earth-orbital test. Planned launch date for the
mission was 15 September 1968
Letter, C. W. Mathews, NASA Ha, to R. F. Thompson, MSG, Earth Orbital Test of
LM&SS, 8 May 1967
"Preliminary Data Specification Document for Missions AAP-1a, AAP-1/AAP-2, and
AAP-3/AAP-4." (MSC/ATSO. June 19, 1967.)
Martin Marietta Corp., Final Report, AAP Mission 14, 60-Day Study, 20 September
1967.
---------
Because of the Apollo 20 accident in January and the resulting program delays,
NASA realigned its Apollo and AAP launch schedules. The new AAP schedule
called for 25 Saturn IB and 14 Saturn V launches. Major hardware for these
launches would be two Workshops flown on Saturn IB vehicles, two Saturn V
Workshops, and three ATMs. Under this new schedule, the first. Workshop
launch would come in January 1969.
NASA Hg Schedule, 24 May 1967
---------
Following a series of discussions on the requirements for the lunar mapping
and survey system (LMSS), the effort was terminated. An immediate stop
work order was issued to the Air Force, the Centers, and the contractors in
the LMSS effort. The original justification for the LMSS, a backup Apollo
site certification capability in the event of Surveyor or Lunar Orbiter
inadequacies, was no longer valid, since at least four Apollo sites had been
certified and the last Lunar Orbiter would, if successful, increase that to
eight.
Memos, Robert C. Seamans, Jr., NASA Ha., to George E. Mueller, NASA Hq., Lunar
Mapping and Survey System (LMSS), July 18, 1967
Seamans to Mueller, Termination of the Lunar Mapping and Survey System, July 25, 1967
---------
In a letter to Satum Apollo Applications Director Charles W. Mathews, MSC’s
AAP Assistant Manager Robert F. Thompson presented Houston’s philosophy
regarding major AAP reprogramming.
Two factors, Thompson said, underlay the necessity for planning alterations:
(1) the likelihood of funding cutbacks during 1968 and 1969 and
(2) a clearer picture of how much Apollo hardware AAP
might inherit, as Apollo reprogramming matured after the 204 accident. Thompson
then set forth MSC’s recommendations for the next phase of AAP planning:
a manned Earth-orbital mission during 1969; two manned flights of 28 and 56
days using the OWS during 1970; a manned AAP/ATM flight during 1971;
long-duration (two months to one year) manned flights during late 1971 and
1972; and manned lunar missions (including surface operations) in the post-
Apollo period. In defining the AAP missions, however, Thompson stressed that
until the Apollo goal of landing on the Moon had been achieved, AAP must be
looked on as an alternate to rather than an addition to the main thrust of
Apollo. It must be clear throughout the NASA manned space flight establishment
that Apollo and AAP would not be overlapping programs and that AAP must
not compete with or detract from the main Apollo design.
Letter, Robert F. Thompson to Charles W. Mathews, Apollo Applications Program
Planning, 29 August 1967
---------
NASA Hg issued a revised AAP schedule incorporating recent budgetary cutbacks.
The schedule reflected the reduction of AAP lunar activity to four missions
and of Saturn V Workshop activity to 17 Saturn IB and 7 Satum V
launches.
There would be two Workshops launched on Saturn IBs, one Saturn V
Workshop, and three ATMs, Launch of the first Workshop was scheduled for
March 1970,
NASA Hq Schedule, 3 October 1967
---------
Apollo Applications Program Director Charles W. Mathews directed the AAP
‘Managers at the three manned space Centers to halt all activity pertaining to the
AAP-IA missions. The purpose of the AAP-1A mission would be to perform
‘experiments in space sciences and advanced applications in a low-altitude Earth
orbit for up to 14 days.
TWX, Charles W. Mathews to Leland F. Belew, MSFC, Robert F. Thompson, MSC,
and Thomas W. Morgan, KSC, Mission 1 Termination, 27 December 1967
---------
NASA budgetary restraints required an additional cut in AAP launches. The
reduced program called for three Saturn IB and three Saturn V launches, in-
cluding one Workshop launched on a Saturn IB, one Saturn V Workshop, and
one ATM, Two lunar missions were planned. Launch of the first Workshop
would be in April 1970.
NASA Hq Schedule, 9 January 1968
---------
NASA released a new AAP launch readiness and delivery schedule. The schedule
decreased the number of Saturn flights to 11 Saturn IB flights and one Saturn V
flight. It called for three Workshops. One of the Workshops would be launched
by a Saturn IB, and another would serve as a backup. The third Workshop
would be launched by a Saturn V. The schedule also included one ATM.
Launch of the first Workshop would be in November 1970, Lunar missions
were no longer planned in the AAP. 3 June 1968
---------
NASA Hg revised AAP delivery and launch schedules, further altering the pro-
gram in light of both changing resources and fiscal climate, as well as a maturing
of program plans per se. The new schedule called for seven Saturn IB and two
Saturn V launches, with flight of the first Workshop slated for July 1972.
NASA Hg Schedule, 13 August 1969; AAP Directive No. 4A, Apollo Applications
Program Work Authorization, 19 August 1969; Apollo Applications Program Specification, 15 August 1969.