Here's the actual timeline from official sources, not the imaginary one in your post:
Source:
https://www.aph.gov.au/api/qon/down...timatesRoundId2-PortfolioId7-QuestionNumber41
Yep, in that 2018 (three years before the program was cancelled) schedule:
Preliminary Design Review– scheduled to conclude in March 2020
Critical Design Review– scheduled to conclude in June 2022
Shore testing of components/propulsion in 2022/23
Construction of the first submarine was due to commence in 2022/23,
Sea trials were due to commence in 2031/32 and acceptance was scheduled for 2032/33
When the Attack Class was cancelled in September 2021:
Preliminary Design Review– uncompleted
Critical Design Review–uncompleted
Construction of the first submarine had slipped to 2025 and Naval Group wanted this to occur in France not Australia
sea trials to commence in '2030's' - date now indeterminate
Acceptance pushed back to 2037
A$2.4bn of the A$3.5bn contracted spend on design and shipyard modernisation spent with no work at Osborne to show for it.
Australia share of the work reduced from 90% contracted in 2016 to Naval Group only promising 60% and was asking for even more of the work to be done in France as well as refusing Australia's request for annual audits of whether the workshare requirement was being met.
Australia was now facing the fact that it had to modernise the Collins class because the Attack Class wouldn't be ready until the late 2030's.
Contract for design and shipyard Osborne shipyard modernisation was signed in June 2016
Order for submarine construction was signed in 2019
October 2019 ANAO audit finds design review meetings running five weeks behind schedule, cant comment on upcoming preliminary design review, considers project on track.
March 2020- Preliminary Design review missed, Naval Group says now expected to be complete in January 2021
Nov 2020 Naval Group asks for fresh 9 month extension to complete the preliminary design review (already was running 9 months late now indicating it will be at least 18 months late) They also informed Keel laying was now delayed from 2023 until 2025.
In Jan 2021 Australia refused to make anymore payments because the program was 18 months behind schedule, construction costs had ballooned from $50bn in 2016 to $90bn 2020 estimate and none of the Osborne shipyard work that it had already made contractual payments for for had been completed. Naval Group implemented a hiring freeze in Cherbourg
In May 2021 Naval Group stopped work on the Attack Class
In Sep 2021 Australia cancelled the submarine.
Canberra has signaled for months it was seeking to walk away over cost blowouts and delays.
www.politico.eu
Anthony Albanese pledges to reset Australia’s strained relationship with France after settling cancelled contract with Naval Group
www.theguardian.com
The demise of the Attack-class submarine paves the way for greater Anglosphere maritime cooperation in the Indo-Pacific. Replacing the Attack-class with a nuclear-propelled submarine signals a new regional challenge to China. [...]
www.internationalaffairs.org.au