Philip Sloss has a new update for Artemis III:
In the latest round-up video, a look at the signs of Artemis activities and progress that NASA published in the past week or so, and how much of that activity is a reminder of long-standing questions about other work needed to fly more astronauts and missions to the Moon.
NASA posted imagery of Artemis III preparations at the Kennedy Space Center, where the SLS boosters are being stacked, the SLS Core Stage RS-25 engines are now installed, and flight crew training is in progress. New pictures and video were published almost daily in the past week, but we have yet to see work on the other two spacecraft and rockets in the Artemis III flight plan.
There's similar mixed signals/messaging when looking at other recent Artemis work disclosed publicly, for example, the start of an Artemis VI SLS build that is simultaneously uncertain to either be finished or fly.
And there's still just as big unknowns about lunar lander and lunar surface spacewalk suit development, with both activity and progress a mystery. (At the end of the week, Blue Origin published another set of renders of their Blue Moon spacecraft concept, while their mission profiles and most of the flight hardware said to be in production remain secret.)
Imagery is courtesy of NASA, except where noted.
Links to social media posts:
https://x.com/ThePrimalDino/status/20...https://www.youtube.com/redirect?ev...Dino/status/2093780692890992821&v=wiQiY4PxBRA
https://x.com/NASASpaceflight/status/...https://www.youtube.com/redirect?ev...ight/status/2094438351856087048&v=wiQiY4PxBRA
Links to stories referenced:
https://www.china-in-space.com/p/chan...https://www.youtube.com/redirect?ev...ge-7-moon-launch-moved-to-early&v=wiQiY4PxBRA
https://arstechnica.com/space/2026/09...https://www.youtube.com/redirect?ev...t-shield-performed-really-well/&v=wiQiY4PxBRA
https://arstechnica.com/space/2026/09...https://www.youtube.com/redirect?ev...hanging-lunar-spacesuit-design/&v=wiQiY4PxBRA
https://spacenews.com/nasa-halts-work...https://www.youtube.com/redirect?ev...ateway-to-develop-a-lunar-base/&v=wiQiY4PxBRA
00:00 Intro
02:19 Artemis III Watch: RS-25 engines all installed
03:34 Boeing's third SLS Core Stage build in the final stretch
12:07 Blog post update on Orion final assembly and crew training
13:24 Welding of the "spacer" continues in Huntsville
14:10 Artemis III SLS Booster stacking continues in the VAB
16:30 Artemis IV Watch: SLS engine section boattail delivered to KSC on Pegasus barge
18:18 Orion ESM modifications suggest specific HLS assignments for Artemis IV
21:13 Other news and notes: Artemis II crew honored and an small update on heatshield performance
23:01 China's next robotic lunar landing mission delayed to next year, 2027
23:25 New SLS Core Stage hardware spotted at MAF Family Day
26:14 NASA descopes lunar spacewalk suit requirements to minimize further delays to Artemis IV
27:02 Congress and the White House start Fiscal Year 2027 with the traditional continuing resolution