If Boeing had the N400's forward section with Saab's tail design then nobody complains I am sure. M346N certainly had a good looking front, too. (But its origin made it a no-go.) T-7A's tail was the golden b-b.
Prime contractor Boeing has a recent history of poor project management, what proof do you have of SAAB as a major cause of T-7 troubles?a lot of my fellow posters here dismiss too easily that Saab unconventional approach and numerous claims of simplified manufacturing and cost decrease were not able to match the reality of the program
Gripen ground equipment has perfectly servicable access ladders. Gripen canopies open just fine.the crude lack of ingress and egress systems that would provide a safe access for both pilots.
Conjecture.Well clearly, Saab early design busted the budget and now Red Hawk stands as a compromised design (until Block II?).
Tried that to no avail.would invite you to read back this thread to close all your bullet points
You seem to know when this type of ladder was introduced.Saab is (was?) a dynamic company and took the bull by the horns nearly in the same lapse of time with a revised access ladder.
The absence of SAAB-specific 'assembly techique' indicates that SAAB is a major cause of T-7 delays and cost-overruns?Saab nut/rivet free composite assembly technique is... Nowhere to be seen!
The fact that it was supposed to be SAABs assembly techniques were able to get the T-7 flying sooner, and then a total redesign that removes them for more traditional techniques does not suggest the cause for the delays?The absence of SAAB-specific 'assembly techique' indicates that SAAB is a major cause of T-7 delays and cost-overruns?
Try again.
I am not aware of the reason for the redesign, a poster here suggested it was for easier/faster production.Fair point, I am not that conversant with the T-7 project.
Was nut/rivet free construction originally considered? If so, when/why was it dropped?
Because of incompatability with Boeing practice/expertise, for instance?
Boeing has now delivered two T-7s to Joint Base San Antonio-Randolph, Texas, where the 99th Flying Training Squadron became the first Air Force unit to receive the Red Hawk in a Jan. 9 ceremony.
Stevens said one aircraft, dubbed APT-5, will be used for “familiarization training,” where a Boeing test pilot will fly with instructor pilots from the 99th to get them acquainted with the Red Hawk. The other aircraft, APT-3, is being used to train maintainers.
The T-7 is currently restricted to flights with test pilots, in test airspace [...] pilots will get qualified on the aircraft through Type 1 aircrew training [in] “early 2027.” Then in spring or summer 2027, the program will start the initial operational test and evaluation phase, where new weapons systems are measured for their operational effectiveness.
Stevens said three more aircraft are further slated for delivery this year. Two will be production-representative test jets, which the Air Force decided to buy last year to provide extra testing capacity. The third will be a developmental jet that will be converted to a test aircraft and delivered to Randolph following electromagnetic testing.
/
Despite the production approval, the Air Force is proceeding cautiously. Each of the first three low-rate production lots will be green-lighted separately, allowing officials to apply lessons from ongoing testing before committing to subsequent batches.
T-7 Red Hawk Moves into Production with $219M Contract to Boeing
https://www.airandspaceforces.com/t-7-red-hawk-production-boeing-contract/
Lots of spare parts (cheap).
Boeing has decided not to bid on the U.S. Navy’s next-generation trainer competition, a surprise move by the company that was seen as a favorite.
The decision allows Boeing to focus more heavily on sixth-generation aircraft programs. With Lockheed Martin having also dropped out of the Undergraduate Jet Training System competition, the teams that remain are Sierra Nevada Co. (SNC) with Northrop Grumman and General Atomics Aeronautical Systems Inc., and a team of Leonardo and Textron.
Boeing in a statement to Aviation Week said its offering, the T-7A Red Hawk, does not meet the Navy’s stated needs despite it already being delivered to the U.S. Air Force.
“Boeing is focused on meeting our commitments, and we bid for programs where we believe we can provide the right solution tailored to our customers’ needs and requirements,” a company spokesperson says. “After careful evaluation, we have determined the T-7A does not meet the U.S. Navy’s Undergraduate Jet Training System requirements.”
Amazing this has been allowed to carry on this long...The first of a series of 3 articles on the T7 and its "issues":
https://breakingdefense.com/2026/06/t7-red-hawk-air-force-trainer-secret-struggles-investigation/
T-38s are life-limited airframes.Amazing this has been allowed to carry on this long...
The ratio of flight hours per week tends to depend on just how much time the engineers need to spend looking at the data produced. (And yes, how much time manglement needs to decide things. Note that Boeing manglement is extremely risk-averse right now.)Boeing has only logged 344 hours of flights in the 8 years since the contract was awarded? Is that a typo? That's 43 hours a year... less than an hour a week. But its ready for the operational tempo that the T-38 replacement will need?
Agree, USAF saw the reduced dollars and thought they had a win but clearly not. When the successful bid is literally billions of dollars cheaper than the two best alternatives it should have sent alarm bells ringing.Not going with the proven T-50 really was a blunder of massive proportions.
Not sure what you are saying with this. Are you inferring the USAF is continuing because they have no other option, which I agree with, or that the USAF persisted too long already?T-38s are life-limited airframes.
"Among other requirements the Air Force claims Boeing “did not flow down” to its suppliers include those for configuration status accounting, which “[p]rovides a detailed audit trail of the aircraft configuration and its evolution over time,” the August 2025 presentation says.The first of a series of 3 articles on the T7 and its "issues":
https://breakingdefense.com/2026/06/t7-red-hawk-air-force-trainer-secret-struggles-investigation/
And we know things happen in threes, T-7, MQ-25 and KC-46. Hopefully this means the F-47 is going to work out for the best but based on the evidence to date that doesn't look promising...What the bloody hell? Boeing has lost control of the program. And the Air Force has lost control of their contractor.
Boeing has now f****d up a trainer even worse than Fairchild Republic did in the 1980s with the T-46.
SecAF should fax eight words to Kelly Ortberg - "Contract Terminated for Default - strong letter to follow".
Things in threes ? MQ-25, T-7 and F-47 are all St. Louis programs. Tell me they have top people in charge.And we know things happen in threes, T-7, MQ-25 and KC-46. Hopefully this means the F-47 is going to work out for the best but based on the evidence to date that doesn't look promising...
Then I think they are cruising towards 6 as their next multiple of 3, because they have also made a biblical mess out of the MH-139 and VC-25B too, so F-47 would make a nice even 6And we know things happen in threes, T-7, MQ-25 and KC-46. Hopefully this means the F-47 is going to work out for the best but based on the evidence to date that doesn't look promising...
VC-25B isn't a Boeing program. All Boeing did was supply completed airframes to Sierra Nevada to convert.Then I think they are cruising towards 6 as their next multiple of 3, because they have also made a biblical mess out of the MH-139 and VC-25B too, so F-47 would make a nice even 6
Both, really.Not sure what you are saying with this. Are you inferring the USAF is continuing because they have no other option, which I agree with, or that the USAF persisted too long already?
but if they stick with Boeing it'll still take another decade to get a trainer to IOC.
Long past time, IMO, but yes.Time for Boeing's senior management to get boot up its' collective arse.
No.VC-25B isn't a Boeing program. All Boeing did was supply completed airframes to Sierra Nevada to convert.
Not so much here, but on other fora under the same username I have been banging a bit of an "anti-Boeing" drum for quite a while but particularly regarding their civils and MAX."Among other requirements the Air Force claims Boeing “did not flow down” to its suppliers include those for configuration status accounting, which “[p]rovides a detailed audit trail of the aircraft configuration and its evolution over time,” the August 2025 presentation says.
"The document says “[c]urrent impacts” of the configuration status accounting problem range from an unknown aircraft configuration to errors ordering parts and inefficient maintenance. In the longer term, the problem raises a host of issues like “runaway sustainment costs,” “compromised airworthiness” and “massive operational disruption,” according to the presentation."
What the bloody hell? Boeing has lost control of the program. And the Air Force has lost control of their contractor.
Boeing has now f****d up a trainer even worse than Fairchild Republic did in the 1980s with the T-46.
SecAF should fax eight words to Kelly Ortberg - "Contract Terminated for Default - strong letter to follow".
Boeing strike again.The first of a series of 3 articles on the T7 and its "issues":
https://breakingdefense.com/2026/06/t7-red-hawk-air-force-trainer-secret-struggles-investigation/
Four actually if you include their space business with the mess that is the Starliner.And we know things happen in threes, T-7, MQ-25 and KC-46. Hopefully this means the F-47 is going to work out for the best but based on the evidence to date that doesn't look promising...
Other challenges have been more mundane. For example, the aircraft currently cannot fly in the rain because exterior access panels don’t seal properly, potentially allowing water to seep in and damage the aircraft’s subsystems.