Open again. Please stick to topic.
Like, it's outright unachievable unless we'll see a dozen aircraft flying early next year, and exactly nothing will go wrong on Turkiye's first fighter aircraft ever. People who declare this delivery target are not faithful to the customer.First delivery target by 2028 gives it 2 years for intensive testing, this is still a bit ambitious for my taste but considering the threat risks involved for the AF, it can't get inducted soon enough...
That was a typo, 28 - 25 = 3Like, it's outright unachievable unless we'll see a dozen aircraft flying early next year, and exactly nothing will go wrong on Turkiye's first fighter aircraft ever. People who declare this delivery target are not faithful to the customer.
2030s is the first likely term, provided that everything goes flawlessly. 2030 may have been a flawless ideal if the first prototype had been an actual prototype, but given its flight rate - it was at best aimed at demonstrating that Turkiye in principle can do it.
Why are you reviving this topic even though we've reached the consensus that the current (P0) prototype has no weapon bays as it is only a ground-test article made airworthy (essentially a technology demonstrator).KAAN P0 - Side weapon bay visible
View attachment 750922
Central internal weapons bay visible, connection points for external pylons also visible on the wing*
View attachment 750923
View: https://x.com/ssysfakb/status/1860007055228305700?t=2EWyfmCFzxqcTj7BytitSA&s=19I heard a comment that "it was almost a different plane," but its accuracy is not certain.
For some reason they decided to repeat this.
P0 has empty space that could be suitable to be a weapons bay, however this doesn't mean that it has one. I have seen them, they are just shut with panels.Why are you reviving this topic even though we've reached the consensus that the current (P0) prototype has no weapon bays as it is only a ground-test article made airworthy (essentially a technology demonstrator).
I couldn't find the exact picture that shows how deep the underbody bay is but even from the angle of the second pic that you've attached, it is visibly not that deep as there's a support structure occupying the majority of the space inside.
View attachment 751132View attachment 751133![]()
View attachment 751138
(I'm currently on the road so considering the circumstances this is the best I could draw on my laptop)
View attachment 751137
Moreover, you can see from the pics above that there are clearly no weapon bay doors, those are just regular maintenance panels on the first prototype.
View: https://x.com/SavunmaTR/status/1653812863641825303
I think @Radonislav had shared that in here before it got deleted.
------
Recently, we've also heard that the second prototype (P1) looks almost nothing like the first (P0, demo) prototype.
View: https://x.com/ssysfakb/status/1860007055228305700?t=2EWyfmCFzxqcTj7BytitSA&s=19
We even have confirmation from multiple officials that the weapon integration and testing activities are only going to begin in 2025 with the roll out of P1.
Well, that was the original plan, so they are sticking to their original plan more than anything.We even have confirmation from multiple officials that the weapon integration and testing activities are only going to begin in 2025 with the roll out of P1.
Full afterburner night shots of Kaan P0
View attachment 751182
View attachment 751183
View: https://x.com/TUSAS_TR/status/1864913209632731478
Edited version -
View attachment 751184
That was not the original planWell, that was the original plan, so they are sticking to their original plan more than anything.
Sorry, but it is, from 2018.That was not the original plan
Please refrain yourself from sharing baseless speculation so that we can keep up the quality of this thread. Moreover, the background of the author doesn't give any credibility to his speculation whatsoever.the article is in turkish but its worth taking a look
written by retired airforce commander
https://www.veryansintv.com/yazar/beyazit-karatas/kose-yazisi/turk-kartali-milli-muharip-ucak-2View attachment 751457View attachment 751455
There's a difference between prototypes and production tooling when it comes to assembly time. Prototypes are often hand-assembled with minimal major tooling to keep everythingHave I misunderstood or will the aircraft not be ready until the end of 2025? And then the maiden flight would take place shortly afterwards.
How do they plan to produce the first series aircraft in 2028/29? 2 years is extremely short, unless they deliver bananaware that only matures with the customer, in this case the Turkish armed forces. Why do they need 8-9 months to build an aircraft?
There's a difference between prototypes and production tooling when it comes to assembly time. Prototypes are often hand-assembled with minimal major tooling to keep everything flying. This means that building one is a lot more time-consuming than telling a running assembly line "print me one more".
GÖKHAN - National Ramjet Powered Air-Air Missile
View attachment 754392
The "National Ramjet Powered Air-Air Missile (GÖKHAN) Development Project" contract was signed between the Ministry of National Defense and TÜBİTAK SAGE on May 21, 2021.
With this project, it is aimed to develop a nationally developed beyond-line-of-sight ramjet-powered air-to-air missile system that will enable the neutralization of various air elements with a long-range engagement in order to establish air superiority, protect high-value aircraft and enable attack aircraft to contribute to survivability by conducting their own defense.
The Conceptual Design Phase and Preliminary Design Phase of the project have been completed, and the Ground Trials Phase activities are being carried out. During the Ground Tests and Flight Tests phases of the project, subsystem and system verification tests will be conducted, and flight and firing tests will be carried out.
With the ramjet-powered air-to-air missile to be developed in the GÖKHAN project, a strategic air-to-air missile system will be introduced to our country, and Türkiye will be among the NATO member countries capable of producing ramjet-powered air-to-air missiles.
https://www.sage.tubitak.gov.tr/en/air-air-missiles/gokhan/
Thats big. 3.6m is the length of most western AAM's in service with 5.1m being an big extension
Way longer than AIM-174B and R-27ER. External only, i guess.Thats big. 3.6m is the length of most western AAM's in service with 5.1m being an big extension
For sure as KAAN would need an IWB with an length of atleast ~5.2m for it. An suboptimal number as its not long enough for 3 SDB (or similiar) or 2 MK.83's.Way longer than AIM-174B and R-27ER. External only, i guess.
That looks impossible.For sure as KAAN would need an IWB with an length of atleast ~5.2m for it. An suboptimal number as its not long enough for 3 SDB (or similiar) or 2 MK.83's.
GÖKHAN - National Ramjet Powered Air-Air Missile
View attachment 754392
The "National Ramjet Powered Air-Air Missile (GÖKHAN) Development Project" contract was signed between the Ministry of National Defense and TÜBİTAK SAGE on May 21, 2021.
With this project, it is aimed to develop a nationally developed beyond-line-of-sight ramjet-powered air-to-air missile system that will enable the neutralization of various air elements with a long-range engagement in order to establish air superiority, protect high-value aircraft and enable attack aircraft to contribute to survivability by conducting their own defense.
The Conceptual Design Phase and Preliminary Design Phase of the project have been completed, and the Ground Trials Phase activities are being carried out. During the Ground Tests and Flight Tests phases of the project, subsystem and system verification tests will be conducted, and flight and firing tests will be carried out.
With the ramjet-powered air-to-air missile to be developed in the GÖKHAN project, a strategic air-to-air missile system will be introduced to our country, and Türkiye will be among the NATO member countries capable of producing ramjet-powered air-to-air missiles.
https://www.sage.tubitak.gov.tr/en/air-air-missiles/gokhan/
https://www.linkedin.com/posts/ibrahim-sünnetci-b2951544_tübi̇tak-sage-ana-yükleniciliğinde-geliştirme-activity-7252627678246174720-Pvcl?utm_source=share&utm_medium=member_iosThe first launching tests of the ramjet-propelled long-range air-to-air missile GÖKHAN, which is under development under the Prime Contractorship of TÜBİTAK SAGE, are expected to be carried out in 2025. However, in order to see the real performance of GÖKHAN, the MURAD AESA Nose Radar, which has a long detection range capability, must also be ready. Because the AN/APG-68 series radars on F-16s will be insufficient in terms of performance for a missile like GÖKHAN. GÖKHAN, which is announced to be able to reach speeds close to Mach 5, will feature the ASELSAN product AGRAS-200AA Active RF Seeker Head.
Except that it's got a liquid fuelled engine.So basically Turkish Meteor AAM.
Thats big. 3.6m is the length of most western AAM's in service with 5.1m being an big extension
I think the person who estimated that made a mistake there.Way longer than AIM-174B and R-27ER. External only, i guess.
Their names were mentioned just to give the audience some idea (mind the parenthesis), the bays are designed around Bozdogan(WVR,, AIM-9XBII equivalent), Gökdogan(BVR, AIM-210C7 equivalent) and Gökhan (Liquid fuel ramjet, Meteor equivalent) missiles.
These indigenous missiles are also not just some copies, while they might look alike, they are thicker than their American equivalents as an example and they also happen to have dual pulse capabilities. They are also launched from the same rails and fed information from the same radar, so it makes sense that they would look similar to American missiles.
https://www.defenceturkey.com/en/co...-test-of-bozdogan-wvr-air-to-air-missile-4490
https://www.defenceturkey.com/en/content/bozdagan-gokdogan-missiles-enter-serial-production-5736
The quoted ranges are open to some speculation though. Army and the Air Force usually give NEZ or (at least near-NEZ ranges) as official figures(this part has been confirmed), and this would be in line with these missiles' and their equivalents' capabilities. But they are never going to publish top secret data though.
![]()
![]()
![]()
Anyway, I hope I managed to clarify some things or at least informed you a little.
It is not the Meteor itself, but Turkey is developing a liquid fuel ramjet BVR missile for Kaan and F-16 Özgür (~indigenous V-level avionics upgrade) with a serial production target by 2028.
I think the current AN/APG-83 of Viper is barely enough for the AIM-120D, so hauling even longer range Meteors would be a waste, imo.
In order to solve this problem, Turkey developed an indigenous GaN radar with slightly more TRMs (~1130) than GaAs APG-83, so I think there might be a considerable capability jump.
But admittedly it's still not the same combo as Typhoon and the Meteor.
View attachment 725810
View attachment 725811
I know it's a stupid question, but has the picture been confirmed to be genuine? The angle has been photographed is strange, as if someone had photographed a Video Photo or Videoclip from the Canvas again.Apparently second prototype; looks like prototype 1 (tech demo) to me
View attachment 755892
View: https://x.com/Defence_Turk/status/1879137731596652575
Even Erdogan's sign on the side panel is the same. Hence this is GTU-0, also known as P0.Apparently second prototype; looks like prototype 1 (tech demo) to me
View attachment 755892
View: https://x.com/Defence_Turk/status/1879137731596652575
I know it's a stupid question, but has the picture been confirmed to be genuine? The angle has been photographed is strange, as if someone had photographed a Video Photo or Videoclip from the Canvas again.
I think the photo as the second prototype is a fake because Erdogan's signature is in the same position as on the first prototype.
Second Kaan Prototype it is then, as the minister states in the video saying "this is the second Kaan, you (people at press event) are the first to see it"Apparently second prototype; looks like prototype 1 (tech demo) to me
View attachment 755892
View: https://x.com/Defence_Turk/status/1879137731596652575