Was gonna quote myself. But it looks you've done it for me insteadTAI TF-X everybody. Hydraulic tests will commence at 17.00 today. Engine integration was done in 2 hours like aforementioned. Fuel system tests were also successful.View attachment 690882
I get his excitement, but Mr. Kotil really needs to chill down a bitBREAKING
TF-X will be able to autonomously return to base in case the pilot faints.
Seems to be the case. The rollout date was postponed slightly.I get his excitement, but Mr. Kotil really needs to chill down a bitBREAKING
TF-X will be able to autonomously return to base in case the pilot faints.He's talking about Auto GCAS. TAI is, in fact, working on autonomous RTB, but it will probably be implemented in later blocks.
BTW, I heard they postponed the roll-out to April to focus on the maiden flight. Is it true?
Hopefully not a small country. We need our own Indonesia in the programme.A foreign country has requested to join the TF-X program!
Agreements will be signed if all goes well.
We will seeHopefully not a small country. We need our own Indonesia in the programme.A foreign country has requested to join the TF-X program!
Agreements will be signed if all goes well.
I think it might be the KSA. A while ago there were rumors that a delegation visited the prototype assembly building. It was the day we got the first leak of the completed prototype.Hopefully not a small country. We need our own Indonesia in the programme.A foreign country has requested to join the TF-X program!
Agreements will be signed if all goes well.
How has CDR not already happened? You need to have the design review before starting to build the partsTF-X's CDR will be completed before the maiden flight.
TAI disagrees with you They do it differently.How has CDR not already happened? You need to have the design review before starting to build the partsTF-X's CDR will be completed before the maiden flight.
Its obviously not a Critical Design Review thenTAI disagrees with you They do it differently.
TAI started producing parts for the TF-X when major design activities were still ongoingIts obviously not a Critical Design Review thenTAI disagrees with you They do it differently.
Design comes before build
That seems like a bad idea to me, and very likely to cost them time and money down the line.TAI started producing parts for the TF-X when major design activities were still ongoingIts obviously not a Critical Design Review thenTAI disagrees with you They do it differently.
Design comes before build![]()
They work in a model which they call as "Cold War development cycle". So from a classical 21st century western aircraft development point of view it may not make sense but since Turkey has put itself in a tight corner, they are trying to accelerate it as much as possible.Its obviously not a Critical Design Review thenTAI disagrees with you They do it differently.
Design comes before build
Program managers over at TAI are pretty confident with what they've come up with. It's worth mentioning that TAI uses Siemens and Dassault softwares at the same time (just to give an example of their unorthodox techniques).That seems like a bad idea to me, and very likely to cost them time and money down the line.TAI started producing parts for the TF-X when major design activities were still ongoingIts obviously not a Critical Design Review thenTAI disagrees with you They do it differently.
Design comes before build![]()
I'm sure they are confident, they wouldn't be doing it otherwise. But that doesn't mean it's the smart thing to do, at least from my point of view. If you don't finish major design before you start making prototypes you risk making the prototypes unrepresentative of the final product. You might still be able to get some valuable data from these prototypes but it also means you'll need to make entirely new prototypes that are representative of the final product and you'll have to redo tests with these new prototypes.Program managers over at TAI are pretty confident with what they've come up with. It's worth mentioning that TAI uses Siemens and Dassault softwares at the same time (just to give an example of their unorthodox techniques).That seems like a bad idea to me, and very likely to cost them time and money down the line.TAI started producing parts for the TF-X when major design activities were still ongoingIts obviously not a Critical Design Review thenTAI disagrees with you They do it differently.
Design comes before build![]()
That is a normal programme. You can further split things up by having graduated PDRs CDRs etc. For more rapid programmes. But it comes with risk of downstream changes having significant cost/time impacts. Aiming for right first time as per B-21 / Hawk is generally a quicker and cheaper way of getting to the final product.TAI started producing parts for the TF-X when major design activities were still ongoing![]()
That's a thing to talk, when we are talking about CDR, are we talking about the screw supplier or who buy the buttons from? Or the airframe design.That is a normal programme. You can further split things up by having graduated PDRs CDRs etc. For more rapid programmes. But it comes with risk of downstream changes having significant cost/time impacts. Aiming for right first time as per B-21 / Hawk is generally a quicker and cheaper way of getting to the final product.TAI started producing parts for the TF-X when major design activities were still ongoing![]()
Is this actually defining CDR as something like 100% parts sign off? And e.g. there's a few cockpit buttons that haven't been done yet...
Using software from multiple providers is also business as usual
When we talk about CDR we obviously are talking about the whole system, ie the aircraft, including the airframe. If the airframe itself is in a frozen state as you're saying then that must be that the critical design is complete, which obviously is not the case here when CDR is not completed yet.That's a thing to talk, when we are talking about CDR, are we talking about the screw supplier or who buy the buttons from? Or the airframe design.
But airframe itself was in a frozen state when it got into production, so different levels of readiness. But we can expect small changes after flight tests
Just my thoughts. To me it sounds like they are building separate prototypes from different design stages. Current prototype and the one that's slated to fly this year sounds more like a Rafale A equivalent (I mean the similarities even go as far as how they are both equipped with interim engines) than, say a F-22 EMD prototypes or F-35 SDD prototypes.I'm sure they are confident, they wouldn't be doing it otherwise. But that doesn't mean it's the smart thing to do, at least from my point of view. If you don't finish major design before you start making prototypes you risk making the prototypes unrepresentative of the final product. You might still be able to get some valuable data from these prototypes but it also means you'll need to make entirely new prototypes that are representative of the final product and you'll have to redo tests with these new prototypes.
There's a reason, for example, the B-21 program has emphasized getting its prototypes as production representative as possible. It reduces risk when shifting to actual production aircraft. And it seems to have really worked for them. I think TAI is really risking having to increase the development period to deal with major design changes made after prototypes were produced, or running into major issues when shifting to production aircraft, or ending up with issues sort of like the concurrency issues the F-35 had but with even greater changes between aircraft.
Just my thoughts. To me it sounds like they are building separate prototypes from different design stages.
Acc. to CEO Kotil's latest statements, CDR is going to be completed before the maiden flight.Just my thoughts. To me it sounds like they are building separate prototypes from different design stages. Current prototype and the one that's slated to fly this year sounds more like a Rafale A equivalent (I mean the similarities even go as far as how they are both equipped with interim engines) than, say a F-22 EMD prototypes or F-35 SDD prototypes.I'm sure they are confident, they wouldn't be doing it otherwise. But that doesn't mean it's the smart thing to do, at least from my point of view. If you don't finish major design before you start making prototypes you risk making the prototypes unrepresentative of the final product. You might still be able to get some valuable data from these prototypes but it also means you'll need to make entirely new prototypes that are representative of the final product and you'll have to redo tests with these new prototypes.
There's a reason, for example, the B-21 program has emphasized getting its prototypes as production representative as possible. It reduces risk when shifting to actual production aircraft. And it seems to have really worked for them. I think TAI is really risking having to increase the development period to deal with major design changes made after prototypes were produced, or running into major issues when shifting to production aircraft, or ending up with issues sort of like the concurrency issues the F-35 had but with even greater changes between aircraft.
Though, who knows, maybe they want to reflect some learnings from the flight test campaign in their critical design for the aircraft. CDR, from what I remember is planned for 2024. They've got some time to do just that by flying the prototype earlier. It's one of their first supersonic, manned, air breathing, combat aircraft after all. Sounds like some valuable experience for the Turkish engineers if we disregard the possibility of added costs. Then again, this program will be the future backbone of their air force so maybe they ain't holding back in terms of budgets. It's not like their parliament is waiting to scream murder if there's any cost overruns unlike in Western countries.
Please go back to the beginning of the thread and start reading instead of coming to the very end and asking. Hell you can even do something as simplistic as googling. It's derailing the thread while we have more important things to discuss.How much funding has the project received so far and how much in the future? Is it known how many foreign engineers have been scalped by Turkey? Also are western "rules based" countries sabotaging the program?
It is impressive. In spite of the downturn in global markets. It is wise to rapidly develop defense industries in these strange times. Over here in America we can look forward to building back better...
Same thing here.Airframe design being frozen was the thing i have heard from them
Then it's almost guaranteed that there would be some changes, big or small, between the earlier and later prototypes.Acc. to CEO Kotil's latest statements, CDR is going to be completed before the maiden flight.
That means the CDR will also be done around a year earlier. So all in all it seems that they are around a year ahead of the original plan.
I mean that makes a lot of sense, they need A LOT of data and the only way to get it is to fly the aircraft as soon and as much as possible. You can't do that if you wait a year or two for the readiness of the intended avionics so you might as well do flight tests now as the plane is already ready. They could simulate the masses which is a common practice.
Airframe design being frozen was the thing i have heard from them
Airframe design outline is something that gets completed by PDR. In critical design you refine the inner details of the aircraft according to the actual designs of the equipments that goes into the aircraft, reflect the actual FLCS, avionics design and OFP, prepare the tooling for prototyping and manufacturing, refine individual components, etc.Same thing here.Airframe design being frozen was the thing i have heard from them