One would kinda expect by 1000 planes built they would be combat ready outside from bombing some toyotas in the desert ,whole story of Israelis with drop tanks and conformal tanks on F35 was BS (no one is fiting anything conformal on an aircraft that has problems with cooling), probably just a cover story for them refueling in a friendly muslim nation that would not like its plebs to know it was colaborating.
From its anonymous digs in Crystal City, the Pentagon’s high-rise civilian annex, the Joint Program Office for the Lockheed Martin F-35 Lightning wrote $36 billion in contracts in 2023 alone. The program is still critical ...
www.aspistrategist.org.au
In 2023 alone, the Joint Program Office for Lockheed Martin’s F-35 Lightning program awarded $36 billion in contracts from its anonymous headquarters in Crystal City, a high-rise civilian building adjacent to the Pentagon. The program remains critical to U.S. military power, even as Boeing’s F-47 steals the spotlight.
The program’s recent performance has drawn sharp criticism from the Air Force, its largest customer, which has yet to approve a new set of critical software for combat use. The problem has compounded the complexities of a comprehensive hardware upgrade called Block 4. The jet also needs an upgraded engine and a new power and cooling system to address a long-standing problem: The F-35 literally overheats in flight.
At the current rate, the last of the 1,763 F-35s the Air Force is scheduled to receive won’t be delivered until 2051. That’s halfway there (full-scale development began in 2001), but the project is under pressure. In its fiscal 2026 budget, the Air Force
cut its planned F-35 purchase from 48 to 24, the lowest since 2015. Chief of Staff Gen. Dave Allwin put it bluntly in a July interview with Defense One that the
service was holding off on the purchase until it could get “the most combat-ready F-35s.”
(Lets screw over our allies ,let them buy , unfinished jets instead of us
let Turkey buy some lemons
)
F-35s delivered starting in 2023 lack combat-ready software. Lockheed Martin said in June that a fix was awaiting Air Force approval. But it’s just the first step in a larger effort to modernize the F-35’s systems under the Block 4 program. The latest estimates put the cost of Block 4 at $16.5 billion, 60 percent more than the Northrop Grumman B-21 bomber. This massive system upgrade effort has also been plagued by delays, and a promised “rethink” plan has never been delivered.
The root cause of the problem is that well-intentioned management encourages competition to replace subsystems when new technologies emerge. This spurs innovation and avoids sole-source contracts. But when program management and Lockheed Martin sought a new integrated central processor in the late 2010s, L3Harris poached incumbent Northrop Grumman, won the contract—and quickly fell behind schedule. The hardware delays delayed software testing. During flight tests in 2023, pilots frequently had to reboot the F-35’s systems midflight.
The embedded CPU is the foundation of the Tech Refresh 3 (TR-3) hardware upgrade, which in turn is the foundation for Block 4. Under Phase 4, more than 80 individual enhancements (including Northrop Grumman’s new APG-85 radar and Raytheon’s EO-DAS 360-degree infrared surveillance system) were scheduled to be introduced into the F-35 production line every two years between the first TR-3 delivery in 2023 and the end of the decade. F-35s ordered in 2029 and delivered in 2031 will meet the Phase 4 standard.
Congress and the Government Accountability Office have repeatedly said that Block 4 is so large that it should be its own major acquisition program, like a program for an entirely new aircraft. But program management continued to operate under the principle of continuous capability development and deployment, adopted in 2019 in keeping with the then-global enthusiasm for “agile” systems development.
But there were too many such subprograms to be implemented in this way, especially since many of them were interdependent. At a hearing in early 2024, Lt. Gen. Michael Schmidt, then director of the Joint Projects Office, testified that the Block 4 project had been “reimagined” and reduced to “the set of capabilities that give us the highest return” because “we believed in pipe dreams.” That reimagining is incomplete — hence the Air Force’s decision to reduce the FY26 order. Outside observers cannot say whether Unit 4 will be launched on the previous schedule, given the reduced set of enhancements.
A parallel program outside Block 4 is addressing thermal management issues that have dogged the program since its first flight tests. One of the design principles of the stealthy F-35 is to siphon heat away from the avionics, actuators, and other systems into either an engine bypass or the fuel and cooling air supplied by the power and thermal management system (PTMS). Otherwise, the internal systems begin to overheat.
In some cases, this heat-dissipation system fails (at higher speeds and lower altitudes), forcing more air from the engine into the PTMS, causing the engine to overheat and shorten its service life. (In 2023 alone, the program office has ordered 40 more engines than the airframe.) Even more efficient cooling is expected to be required for Block 4 and beyond.
Part of the solution was to equip the F-35 with a new engine design. By 2022, this was to be an efficient but technically challenging configuration called an “adaptive cycle.” But such an engine would be difficult to fit into the short takeoff and vertical landing version of the fighter, the F-35B, and Pratt & Whitney had lobbied hard to improve the F135 engine already in use on the F-35 with a new high-pressure section. A contract for the engine upgrade was awarded in 2023, with the aim of delivering the engines by 2029. However, in June 2025, it was revealed that a critical design milestone for the engine upgrade, scheduled for this summer, had been delayed by a year.
The second front in the thermal war is the introduction of a new PTMS design, with Lockheed Martin hosting a competition between RTX Collins and the incumbent Honeywell. The PTMS is a complex system combining environmental control, auxiliary and emergency power, and engine start.
The timeline for introducing these new technologies into production is unknown,
but another question arises: what to do with the more than 1,000 F-35s built before TR-3, including those operated by Australia, South Korea, Japan, and Singapore? Upgrading even half of those aircraft to Block 4 standards with engine improvements and the new PTMS would be the largest aircraft upgrade program in history, and the unit cost is unknown.
And with the U.S. Air Force seemingly ready to switch to Boeing’s F-47, Lockheed Martin CEO Jim Ticlet is talking about a future F-35 variant that could incorporate technology the company developed for its failed F-47 competitor. The technology could provide “80 percent of the capability at 50 percent of the cost per aircraft.” Ultimately, 3,500 of these [F-35] landing gears will be built, at varying stages of technology and capabilities.
That sounds less like a Block 4 and more like an entirely new avionics suite — perhaps based on what Northrop Grumman is developing for the B-21 — and an adaptive engine that would provide more efficient cooling and increase range by 30 percent. Some of the aircraft could be upgraded, but the option is to build a new production version with a larger wing like the current F-35C and upgrade it by eliminating the short takeoff and vertical landing capability.
It’s a solid strategy because the Air Force and Navy must continue to buy F-35s to keep their fighter forces from becoming obsolete. The F-47 would be too expensive and too late, and the Defense Department is unwilling to fund the Navy’s new fighter, the F/A-XX.
Even if the Air Force were looking for an entirely new entry-level fighter to complement the F-47, it’s unlikely that any of the three possible suppliers would want to build one: Lockheed Martin would be happy to build an updated F-35, Northrop Grumman, the F-35’s production partner, would likely be of the same mind, and Boeing would be focused on the F-47.
That means the new entry-level fighter would have to be the significantly improved F-35 that Lockheed Martin is talking about. How that would fit in with the Block 4 upgrades and refits is anyone’s guess.
Either way, the F-35 is here to stay for a long time.