PD-214 Security Class Maritime Administration conceptual mobilisation ship 1974-1981

A Tentative Fleet Plan

I really should change my personal text
Joined
9 April 2018
Messages
1,184
Reaction score
2,678
Source: p474-p475, US Amphibious Ships and Craft, Norman Friedman

The Center of Naval Analyses (CNA) compared a number of different ship designs for the role of the Maritime Prepositioning Squadron (MPS). One of these was the PD-214 "Security Class" (C8-M-MA134), a conceptual mobilisation ship, the design of which was started by the Maritime Administration in 1974, with the preliminary design being completed in 1978, and the contract design was being completed in 1980, at the time CNA's MPS study was taking place. As the navy had no MPS design to hand, the PD-214 was to be modified to meet the requirement. PD-214 was a break-bulk ship due to the assumption that it might have deliver cargo to areas without elaborate container facilities, and some military equipment including tanks could not be carried inside standard containers.

In August of 1980, NAVSEA began to modify the Jumbo PD-214 (C8-M-MA134J) into a mobilisation ship referred to as TAKX. Defence features included decks strengthened for 60-ton tanks, a stern ramp and heavy cranes to permit the ship to unload herself. Lighterage would be 4x powered causeways, 6x unpowered causeways, 2x LCM(8)s and a side-warping tug to install the necessary bulk fuel distribution system. The ship would have a CH-53-size helicopter pad and could offload LVTs down her stern ramp. (I've placed the changes in dimensions and capacity into the table. The original in Friedman only compared the PD-214, Jumbo PD-214, the Maine and the Waterman Line's modified Maine)

In August of 1980 it was expected that the first TAKX would be included in the FY81 program, and requests for proposals were expected shortly. It would take 12 Maines or 15 PD-214s to support the three Marine Amphibious Brigades that made up an MPS. Estimated operating and acquisition costs for FY81-87 were $4.1 and $4.3 billion respectively, with the necessary squadrons being placed into service in 1983, 1985 and 1987.

By 1980, the four-year defence plan called for the conversion of 4 Maines and buying 8 PD-214s. The original plan had been to buy 15 TAKXs, at a unit price of $103.5 million, but numbers were cut when this rose above $174 million. As submitted, the FY81 budget called for a lead ship plus $33 million for the long-lead items of a second. Congress initially authorised two TAKXs, but then stalled after several shipping lines saw this program as a way to offload surplus shipping, including the Waterman Line's three enlarged Maines (originally built for trade with the Soviet Union, which was now collapsing after the invasion of Afghanistan) and Sealand's eight SL-7s. Apparently several Congressmembers confused Maritime Prepositioning and Sealift requirements, the Navy budget was cut and was told to choose between the SL-7s and Prepositioning ships. The SL-7s were not in the original FY81 program, and were not authorised by the House, but were pushed hard by the Senate, and thus survived in the Defence program. In May 1981, the Reagan Administration killed off TAKX, as competing priorities meant there was no money for it, and decided to convert and charter civilian ships to fill the MPS role.

PD-214 (C8-M-MA134)Jumbo PD-214 (C8-M-MA134J)TAKXMaine (C7-S-95A)Waterman (C7-S-133A)
Length (ft)560/609670/719831ft 6in oa640640
Beam (ft)9797105.5102105.5
Draft (ft)3030NA3233
Displacement (tons)28,87037,80020,860 (light), 48,860 (loaded)33,76538,500
Power (SHP)22,50022,500NA37,00032,000
Speed (kt)21.521.5NA2320.9
Capacity (sq ft)NANA170,000144,77062,025
Dry Capacity (cu ft)NANA400,000158,800*1,039,550
Liquid Capacity (cu ft)NANA(from text 1.9 million gallons) approx 254,000 cu ft28,33013,229
Lengths for the PD-214s are between perpendiculars and overall respectively.
*Dry cargo can be substituted for vehicles, thereby increasing cu ft to 153,360.

Does anyone happen to know more about the PD-214 mobilisation ship, or TAKX?
 
Last edited:
What's a "mobilization ship"? Also, do you own the book, or do you have the PDF copy that's been going around for the past couple of years?
 
What's a "mobilization ship"?

It's a ship design intended to be rapidly manufactured in wartime or the runup to a conflict, and to replace wartime.losses after a war was over. Basically a modern version of the Liberty ship concept.

I think in the case of PD-214, they also hoped that shippers would adopt the concept in peacetime, creating a pool of ships that could be readily adapted to military use in wartime. In practice, they ended up paying shippers to add militarily useful features to their own designs instead and subsidized their operations.
 
What's a "mobilization ship"? Also, do you own the book, or do you have the PDF copy that's been going around for the past couple of years?
I own the book.
Where did you get it from? All the copies I find are like $300.

I can't speak for ATFP but I have one as well. I bought it new, when it was still in print. These days. there isn't much supply, though Abe Books is showing one for just under $200 and eBay has one for $135.

It looks like the Naval Institute Press is doing reprints of some of Dr. Friedman's other design history books. No Amphibious Ships yet but it might be coming sometime. (Personally, I'm looking for "US Small Combatants" but the demand can't be strong enough to support a reprint.)
 
Last edited:
Try bookfinder, or abebooks. Prices start at ± $200, or, as TomS finds, $135 on ebay.
 
I will point out that I did pay a ridiculous amount both for Amphibious Ships and Craft and Small Combatants, but at this point they are by far my most-read Friedmans, I would suggest waiting for a reprint, hopefully there will be enough demand for USNI to consider doing so.
 
I will point out that I did pay a ridiculous amount both for Amphibious Ships and Craft and Small Combatants, but at this point they are by far my most-read Friedmans, I would suggest waiting for a reprint, hopefully there will be enough demand for USNI to consider doing so.
Yeah, and I don’t have that kind of money. Looks like I’ll be getting my first job this summer then! :)
 
I will point out that I did pay a ridiculous amount both for Amphibious Ships and Craft and Small Combatants, but at this point they are by far my most-read Friedmans, I would suggest waiting for a reprint, hopefully there will be enough demand for USNI to consider doing so.
Yeah, and I don’t have that kind of money. Looks like I’ll be getting my first job this summer then! :)
I got my copy of "Small Combatants" at a very reasonable price. It was not a pristine copy, and I had to wait several years before I saw it at a price I was willing to pay. But I got it. Just keep looking around.
 
More information on the evolution of the PD-214 design in the link below:


September 15, 1980 - Maritime Reporter and Engineering

An Update On The Contract Design of the Multi-Purpose Mobilization Ship​


George H. Levine and John F. Walter​


One of the Maritime Administration's (MarAd) missions is to provide shipping capability during a declared national emergency.

As one part of this mission MarAd has identified the need to have "on-the-shelf" plans and specifications for designs which will satisfy shipping requirements.

MarAd initiated a "Ship-Designs for Mobilization" program in 1974 to identify these requirements. Ship characteristics were developed through an analysis of potential emergency shipping needs, shipyard production capabilities, and a variety of design constraints and requirements.

This paper presents the present status of the contract design phase and the original preliminary design of the Multi-Purpose Mobilization Ship along with three alternative versions showing possible configurations utilizing optional features. This particular design provides flexibility and versatility to effectively handle and stow containerized, roll-on / rolloff, unitized, breakbulk, or heavylift type cargoes. The design is commercially attractive in trading with developing areas, although it cannot compete with dedicated sophisticated designs in specialized trades.

The five scheduled phases of this design project are: Phase 1 — Development of mobilization ship capabilities ; Phase 2 — Preliminary design of mobilization ship; Phase 3 — Contract design of mobilization ship; Phase 4 — Construction of prototype, and Phase 5—Operation of prototype.

The first phase has been completed and has resulted in the development of working papers reviewing: Needed shipping capabilities ; shipyard production problems, engineering system alternatives ; possible ship concepts, and design constraints.

The second phase has also been completed. It began with the development of three conceptual designs— the PD-204 versatile general cargo mobilization designs.

These cargo ships were planned as candidates for the basic building blocks of the mobilization fleet. These designs were developed through the concept stages to assure feasibility. The three designs offered a variety of ship sizes and cargo-handling arrangements.

Features of the three designs developed were compared with each other for their particular advantages and disadvantages.

The small PD-204 design, "500 General," featured a 489-foot LBP and 73.5-foot beam vessel with five general cargo holds.

The large PD-204 design, "670 RO/RO," had a 655-foot LBP and 105-foot beam and was designed primarily for roll-on / roll-off cargo.

The middle sized "550 Combination," on the other hand, was 539-feet in LBP and 97-feet in beam and had a multipurpose cargo-handling approach. Eight holds with 'tween decks were serviced by cranes (or kingposts and booms) with hatch covers forming a container-guide structure, which when in a vertical position, allows easy loading of containers.

A stern ramp was also provided for roll-on/roll-off cargo access to the second deck.

Efforts between August 1977 and November 1978 refined the 550 Combination design into the Multi-Purpose Mobilization Ship preliminary design, PD-214.

In September 1979 a contract was awarded to M. Rosenblatt & Son, Inc. to prepare the contract design of the base ship and a number of alternative versions utilizing various optional types of propulsion machinery and cargo gear. This work is scheduled to be completed some time after the presentation of this paper.

The preliminary design was the starting point for developing the contract design. The object of the contract design phase is to complete the preparation of plans and specifications to a level of detail adequate for a shipyard to produce a bid quotation to construct the ship.

As a result of the Government/ Industry Mobilization Ship Conference in November 1978, numerous comments were received which indicated that the preliminary design was too small for both commercial and military operations.

Comparison with the results of MarAd R&D study on the design of the next generation cargo liner also indicated that a larger vessel would be more appropriate for commercial use. This R&D study is particularly valid since it was done in cooperation with seven ship operators.

It was concluded that the new contract design base ship length should be the same as the preliminary design jumbo. In addition, the beam was increased to 105 feet 6 inches. It became apparent that, for more efficient container stowage, the hull depth should be increased to 70 feet, and it was decided to use flush, mechanically operated hatch covers on the weather deck and to include a ramp to allow vehicle access to the weather deck. Finally, the hull material was changed from mild steel to high strength steel when it was found to be readily available in mobilization situations. The design is shown in Figure 1.

General Arrangement​


The preliminary design of the Multi-Purpose Mobilization Ship is a single-screw ship capable of loading, transporting, and discharging a mix of roll-on/roll-off, general breakbulk, unitized, and containerized cargo. The house and engine room are located aft.

The machinery space is designed to accommodate any of various types of main propulsion machinery plants of the required horsepower necessary to provide a minimum 20-knot speed.

In determining the degree of automation to be used for the machinery, the dichotomy between the desire for simplicity of design and construction (requiring less automation but increased manning) versus the limited availability of trained shipboard engineering personnel (dictating decreased manning and increased automation) during an emergency must be considered.

The "one-man" watch concept selected for all mobilization ship powerplants appears to be a reasonable compromise.

All configurations of the mobilization ship can be lengthened.

The jumbo Multi-Purpose Mobilization Ship version prepared during the preliminary design added one complete cargo hold of 110 feet, with associated cargo-handling gear, to the base ship. Speed remains above 20 knots.

The Multi-Purpose Mobilization Ship design can handle general breakbulk cargo, containerized cargo and ro/ro cargoes. Some of the commercial cargoes that can be driven on are buses, trucks and cars. Containers can be lifted onboard using shipboard cranes or carried on by straddle carrier or forklift. Palletized cargo, such as oil drums and cartons, can be carried aboard using forklifts or lifted aboard. Paper rolls, cable reels, lumber bales, and random lengths of pipe can all be easily handled.

Military cargo items, such as M60 tanks, can be loaded over the ramp or hoisted onboard, using the twin-tandem heavy-lift capability.

Cargo type helicopters also can be lifted or rolled aboard.

Trucks and other wheeled vehicles can be quickly loaded and discharged over the ramp. The portable cardeck can accommodate jeeps in the ro/ro space.

Overall, the ship has enough capacity to carry supplies and equipment for one Army battalion.

A 114-foot slewing stern ramp is installed to provide access to the ro/ro deck (Second Deck). It is hinged to a turntable, allowing it to rotate so that the vessel can be offloaded when either port or starboard side is adjacent to the berth. It is 24-feet wide, permitting two-way truck traffic. Two sideports are also provided to allow allow additional ro/ro access to the Second Deck.

From the Second Deck an internal ramp in Hold 4 allows rolling cargo access to the Third Deck. In Hold 3 a ramp goes down to the Tank Top. The Third Deck ramp is 18-feet wide and the ramp to the Tank Top is 14-feet wide.

Portable cardecks are installed in the Second Deck ro/ro area.

These are lowered and form a deck with a 5-foot overhead clearance, so that maximum utilization of space can be realized when carrying automobiles.

Since in wartime mobilization situations manufacturing capacity may not be adequate to supply the necessary numbers of sophisticated cargo gear such as deck cranes and slewing ramps, provision has been made in the design to incorporate alternative gear.

For instance, a quarter ramp or a single straight stern ramp could be utilized. Instead of deck cranes it would be possible to utilize kingposts and booms. Another alternative capability that has been included is the installation of a gantry crane instead of the deck cranes. Depending on the amount of ro/ro capability required, internal ramps to the Tank Top and/or Third Deck and watertight doors between holds could be omitted. Likewise, watertight doors can be added to increase the ro/ro capability into the forward holds.

Machinery Selection​


Machinery considerations for the Multi-Purpose Mobilization Ship preliminary design were generally dictated by the environment in which the vessel was expected to be constructed. Since the ship is intended to be rapidly built during a full-scale wartime mobilization for military support, or to serve as replacement tonnage of U.S. ship losses for postwar commercial trade, simplicity and efficiency are characteristics required of the machinery plant to satisfy this operating profile.

Normally, a propulsion system most compatible with the ship's mission would be selected on the basis of trade-off studies, considering space, weight and arrangement requirements, fuel consumption and costs. However, since the production of the maximum number of ships in the least time is a major planning objective, tradeoff studies to determine the optimum powerplant are less important.

Since production capacity for a particular type of machinery is limited, designing the vessel to accommodate several different types of powerplants increases the number of ships that can be constructed in a given time frame.

The combined criteria of availability, marine service experience and design simplicity led to consideration of the following machinery alternatives for the preliminary design of the mobilization ship: Steam turbine; medium-speed diesel; slow-speed diesel; heavy-duty and aircraft derivative gas turbine prime movers, with geared (or direct-drive, in the case of the slow-speed diesel) transmission systems, and fixed-pitch propellers.

Transient Personnel​


A comment received from the military community suggested that, for mobilization purposes, provision should be made for the carriage of 50 transient personnel in addition to the ship's base crew. Based on recent studies, modular accommodations aft of the deckhouse would meet this requirement.

The facility is intended to be as completely self-contained as feasible. The modules would be the same size as I.S.O. shipping containers.

The accommodation complex consists of 21 modules above the Main Deck for berthing, galley, messroom, lavatory, stores, laundry and recreation; interconnected by stairways and passageways. A sewage module, consisting of a sewage holding tank and pumps, receives drains from sinks, showers, lavatories, etc., and would be located aft the house below the Main Deck. The lavatory and galley modules would be equipped with internal plumbing supplied from the ship's fresh water system.

Lighting, HVAC units, refrigeration equipment and hot water heaters would be supplied in appropriate modules and would consume ship's service electrical power by means of plug-in connections.

Maritime Reporter Magazine, page 14, Sep 15, 1980

1000006414.png

Another view of a model of the PD-214 design is in the below article on mobilization barges:


1000006416.png

It also states the following:
For the “Jumbo” version of the multi-purpose
mobilization ship, which is preferred by the U.S. NAVY
and the Military Sealift Command, there exist only 33
building ways or basins at major U.S. shipyards with the
required construction capability. Full utilization of large
basins allows total construction capability of 48 of these
ships simultaneously. Estimated construction time for
the mobilization ship is 17 months in a Mobilization
Period.
 
Last edited:

Similar threads

Please donate to support the forum.

Back
Top Bottom